Lower Knapp Farm

Swimming Pool Upgrade & Refurbishment

Project Value: £750k 
Programme: 13 weeks

Client Team -  Architect - Conker Interiors Ltd
                      Engineer - Sands

​

Work Description -
This project was to upgrade and refurbish a pool hall, along with toilets and changing facilities within a holiday complex.
As the pool pipework was undersized and the pool surrounds had sunk, specialist sub-contractors were precured to stabilise the ground allowing trenching works to be carried out to upgrade the pool systems.


Works to upgrade the building could then take place working with the clients interior designers. 